Construction – Project
Construction & Installation of Well Site Facilities – Khazzan Gas Project phase 1 and phase 2
Client: BP Oman
End User: BP Oman
Scope:
Civil, Mechanical, Electrical & Instrumentation Construction

Peak Manpower
180 Numbers
Total Man Hours
3 million
Years
2015 to 2021
CMEI works for Construction, Fabrication, installation, and pre-commissioning of all well site facilities (equipment and utilities) required for both the Gas Production Wells and the Water Disposal Wells (Phase 1 – 56 wells, Phase 2 – 40 wells). STS shall pre-fabricate the well site facility components at STS fabrication facility in Nizwa and then install them at the Khazzan worksite. The Skid and Tie-in spool assembly arrangements to be assembled fully piped and wired as final packages, inspected and tested prior to dispatch for installation at site. The well site facilities include Well head process module skid, Utilities skid, Tie-in spools assemblies, Electrical RMU and 3.3kV/0.435kV Transformer.








