Service Contract – Project

General Construction Services Contract form BAPCO Upstream

Client: BAPCO Upstream
End User: BAPCO
Scope:
EPCC Service Contract – Construction
Peak Manpower

600 Numbers

Total Man Hours

8.830 Million
(as of Jan 2025)

Execution Timeline

2023 to 2026

To carry out all surface facility construction activities associated with the Bahrain Oilfield development, includes civil, mechanical and E&I works, well pad preparation, earthworks, mechanical / E&I well hook-up and flow line works to field tank battery limits.

  • Well Pad Preparation = 144 pads
  • Khuff well pad preparation & Cellar construction = 16 wells
  • Foundation and Sleeper works for GTN & RCS
  • Installation of Surface Facilities and Pipelines for well including road crossing works = 180 Wells
  • Re-routing the pipeline = 40 Wells
  • Pipeline construction for steam & production line in offsite & inter connecting piping works
  • GDN 24” & 28” dia pipeline construction  in offsite & inter connecting piping works
  • Hookup work for BPU SOW electrical hook up of BPU – 75 Nos
  • Installation of PT’s at Remote Well Manifold = 32 Nos.
  • Panel board Installation
  • Switch gear installation,Mini sub-station building electrical works
  • Automation of facilities like Well pad, well manifolds, tank batteries etc.
  • Installation of Radio communication elements.