Maintenance – Project
Refinery 1 Plant & Polypropylene Plant (PP) TA 2023
Client: OQ Oman
Scope: Turnaround/Shutdown
Carry out the Main Mechanical works in SR1 & Polypropylene Plant (PP) TA during 2023 turnaround.
Execution Timeline
2023
Peak Manpower
5,700 Nos.
Total Man Hours
3.46 million
Shutdown Duration
40 Days