Maintenance – Project
Sohar Refinery 2 Plant Turnaround 2022
Client: OQ Oman
Scope: Turnaround/Shutdown
Mechanical Maintenance Works for the below units during Sohar Refinery 2 (SR2) Plant Turnaround.
Execution Timeline
2022
Peak Manpower
3,678 Nos.
Total Man Hours
1.94 million
Shutdown Duration
18 Days